Third Marsa flyover to be completed today, weather permitting

Thursday, 12 December 2019, 12:10 Last update: about 5 years ago

The third of seven flyovers forming part of the Marsa junction is set to be completed today, weather permitting, Infrastructure Malta said on Facebook.

It is the longest flyover in the €70m project at 227 metres joining the highest part of the first flyover in Triq Aldo Moro, eliminating traffic lights. 

The first two interconnected flyovers were inaugurated in September, linking Marsa to Luqa.  The new flyover will initially only handle southbound traffic, from Marsa to Sta Lucija while work continues on the lanes at ground level to link with the other flyovers. When the structures are ready, the flyover will be used in the northbound direction, from Sta Lucija to Aldo Moro Road 

All four remaining flyovers are expected to be in use by June. The whole project is due for completion by the end of next year.