The scaffolding on Manuel Dimech Bridge will be erected next week and a traffic management system will be implemented as from early December, said Urban Development and Roads Minister Jesmond Mugliett yesterday.
Minister Mugliett, who was speaking at a public consultation meeting yesterday, appealed to all the stakeholders and the public to give their full cooperation while the reconstruction of the bridge takes place.
“Even though the project is starting slightly later than we estimated, we wanted to ensure that everything was in place before the work began,” he said.
An extensive traffic management plan had to be drawn up and at least Lm214,000 worth of road patching had to be done before the reconstruction starts, he added.
“Everything will be ready, with no foreseen hiccups once the works begins,” said Mr Mugliett. The scaffolding will be erected next week, but traffic will flow as usual as no roads will be closed, he explained.
“The traffic management system will be implemented in early December – therefore there will only be 10 months of traffic disruption,” said Minister Mugliett.
While work is taking place on one of the decks, the other deck will be open to vehicles on a two-way traffic single carriageway.
Although it was hoped to continue construction for 24 hours a day, the Malta Environment and Planning Authority (Mepa) issued a permit for 12 hours. However, following further consultation said Minister Mugliett, Mepa had agreed to extend it to 18 hours.
The bridge is 130m long and carries around 1,700 vehicles an hour during peak times, said Mr Mugliett.
Project architect Malcolm Gingell said that it had been decided to demolish the bridge and construct a new one using post-tension technology, as the substructure is damaged at several points. The new bridge will be constructed on site, using around 2,400 cubic metres of concrete.
Malta Transport Authority (ADT) official Lara Demicoli explained the traffic management scheme that will be implemented when work begins and said the ADT are encouraging people not to use the bridge at all but to use the alternative routes instead.
She said alternative routes for various localities will be announced in the local media in the near future. Traffic will be allowed in the roads underneath the viaduct and both tunnels will remain open to traffic.
Mr Mugliett added that the large majority of traffic stoppages will be due to the transportation of concrete to the site from the two local plants.
“Since the concrete has to be taken on-site within a short time frame, traffic police will regulate traffic to allow the cement trucks quicker access,” he said.
A member of San Gwann local council suggested setting up the concrete plants underneath the bridge to eliminate the need for transportation.
However, Mr Mugliett explained that, due to certain restrictions imposed by Mepa, this was not possible. He reassured the public that only really necessary stoppages will be made, to reduce any disturbance to the flow of traffic.
One man suggested reducing the speed limit on the bridge from 45km to 40km due to the size of the project and the possible bottleneck created by one-way traffic. He asked if a contingency plan had been drawn up to allow the emergency services to arrive at the scene of an accident in the tunnel.
Ms Demicoli explained that the speed limit will be kept at 45km as the majority of drivers are used to driving at that speed, especially because of the speed cameras.
She added that the lanes will be divided by plastic barriers that can be removed in case of an emergency.
She added that temporary directional signage with a yellow background will be installed at critical junctions, warning drivers about the project and encouraging them to take alternative routes well in advance.
One man pointed out that there are around 25 schools in the Pembroke and Sliema area.
“Most of the school transport for those schools uses the Regional Road. Heavy vehicles should not be allowed to pass through that area but should be redirected on to different routes,” he said.
Malta Transport Authority CEO Gianfranco Selvaggi said that this was a valuable suggestion and it would be taken into consideration.
A Kappara resident asked Minister Mugliett whether, in view of its disastrous state, Sliema Road will be patched up before the reconstruction work begins.
Mr Mugliett replied that it still has to be decided if the road is to be patched up or if further work is required.
Assistant Police Commissioner Josie Brincat suggested closing off access to Regional Road from the Kappara roundabout between 6.30am and 9am due to the heavy volume of traffic, and instructing drivers to take alternative routes.
“At present, huge tailbacks are created in the morning due to criss-crossing at the roundabout, let alone when reconstruction of the bridge starts,” he said.
Minister Mugliett and Mr Selvaggi said that AC Brincat’s suggestion would be taken into consideration.