Additional work that has become necessary has meant that the cost of reconstructing the St Paul’s Bay bypass has increased by Lm454,000 to an estimated total of Lm3 million, Transport Minister Jesmond Mugliett told Carmelo Abela.
Mr Mugliett explained the various
reasons for the cost over-run:
• the underlying bed was found to be very weak and varied to a considerable degree from place to place, thus the whole structure of the road has had to be replaced;
• a French drain has had to be introduced to collect the water coursing down from Wardija to ensure that this does not damage the reconstructed road itself;
• there has been an increase in costs relating to changes and/or installation of services of various bodies;
• the introduction or the reinforcing of retaining walls; and
• a Lm273,000 contingency (10 per cent) has had to be provided due to the possibility of further changes which may be seen to be necessary as the project progresses.
Mr Mugliett also explained that this estimate does not include work that has to be done in the Tal-Fjuri area and landscaping work along the road.