The eastern viaduct of the Manwel Dimech Bridge – that leading from Paceville to Msida – will be closed on Monday when work on the bridge project is finally expected to kick off.
The work was first targeted to start in September but a number of hitches, described as “logistical problems”, delayed the commencement of work. It is expected to be concluded late next year.
When the eastern viaduct is closed, the other side of the road will be changed to a two-way, one-lane traffic system. This could, however, increase traffic delays and the use of alternative routes is recommended.
Sources close to the Urban Development and Roads Ministry told The Malta Independent that the traffic management plans will be extensively publicised in the coming days.
Adverts in the Sunday papers have been booked showing the full list of alternative routes that motorists are being advised to use in order to limit delays and minimise problems. Notwithstanding this, motorists are urged to avoid the area unless absolutely necessary.
Variable Message Signs – electronic roadside message boards that can show different messages depending on the circumstances – will be used during this project.
The Manuel Dimech Bridge was built by Taiwanese workers in the 1970s. Over the past few years, in-depth studies were carried out on the structure and it was decided that the structural columns were to remain in place, however all the road decks had to be replaced. The bridge’s columns will be strengthened but not replaced.
The project will also include the re-alignment of the adjoining roads.
The project, worth around e6 million and which will be funded by the European Union’s European Regional and Development Fund, is expected to take 52 weeks to be completed. The contract has been awarded to the BCP joint venture composed of two Maltese companies and an Italian one.
These companies are: Maltese companies Bonnici Brothers and C+F Ltd, which have paired up with Italian civil engineering firm Procom Srl.