The Enemalta Corporation has published its plans for the purchase of a new power plant, or the electricity generated from a new locally-based power plant – the main requirements are that it is capable of being continuously operated on liquid fossil fuels as its main energy source, that its output capacity will not be less than 100 megawatts in summer, and that it will be able to be converted to natural gas firing in the future.
As such, Enemalta is considering two options for the project’s implementation: a build-and-transfer contract, which would consist of a turnkey contract for the supply and construction of the plant, and a build-own-and-operate contract, which would see the successful bidder entering into a power purchase agreement with Enemalta.
Enemalta stated that candidates can also provide alternatives to the two options “provided the scope of the whole procurement is achieved”.
The new power plant, Enemalta stipulated, is to be located either at Enemalta’s Delimara Power Station site or in any other suitable alternative area outside the parameters of Enemalta’s two power station sites, provided that all permits for its location are obtained from the competent authorities. Should bidders prefer a location at the Delimara facility, Enemalta has designated a specific area measuring 74x52 metres for the construction of the new plant.
All offers for the construction of the new plant will have to “be capable of being continuously operated on liquid fossil fuels as the main energy source”. Enemalta also stipulated that the plant is to be capable of being converted to natural gas firing in the future.
Such liquid fossil fuels used currently for the generation of electricity are heavy fuel containing one per cent sulphur, and light distillate (gasoil) with a maximum 0.2 per cent sulphur content. As from 1 January 2008, gasoil’s sulphur content will have to be brought down to 0.1 per cent by mass.
If the candidate deems such fuels inappropriate, Enemalta will consider the use of alternate fuels, provided the fuel in question is in line with EU and Maltese legislation. If the candidate for the new plant selects an alternative fuel, the candidate would have to provide for the supply and local storage of the alternative fuel. However, the Corporation made it clear that the availability of other storage sites at the Delimara power station “is extremely limited”.
As such, if an alternative fuel is to be used for the new plant, it would undoubtedly have to be within the context of a third power plant site, in addition to Marsa and Delimara, or with the fuel being stored off site.
A clarification meeting will be held between Enemalta and prospective candidates on 15 December, while the closing date for bids will be set for 20 February 2007. With a maximum two-year timeframe being allotted for the project, it can be presumed the new plant will begin operations sometime in 2009.
What is referred to as a “prior indicative notice for supply contract” was issued quietly last week in the government’s verbose public call for tenders. Enemalta is currently in the process of drawing up a full contract notice, which is expected to be issued by the year’s end.
Laying out the primary criteria to be met by the new plant, Enemalta made it clear that it intends to increase the “locally installed available generating capacity with an additional power plant connected to its electrical network” and that any such plant will need to have a net continuous electrical power output of not less than 100 megawatts in summer.
As such, the plant will constitute a third power generation facility for Malta, not a replacement of any existing facility, since the 100 megawatt minimum threshold hardly compares with Delimara’s current total generating capacity of 304 megawatts or Marsa’s 267 megawatts.
At 100 megawatts, the new power plant would augment Malta’s maximum power supply, currently 571 megawatts, by 17.5 per cent.
The contract will be awarded to the “most economically advantageous bid, measured as price/kWh in terms of lifetime costs over the evaluation period, among all technically and contractually acceptable offers”.
At this preliminary stage, candidates are expected to submit an outline proposal, which, if deemed acceptable, will lead the candidate to being chosen to proceed to the negotiation stage.
From the prior indicative notice published by Enemalta, the Corporation appears to be seeking top-notch candidates and, given the experience requirements, it seems the contract holds little scope for Maltese companies.
Enemalta will require any candidate, or the leading member of a joint venture or consortium, to have a 10-year track record in generation plant construction and have available management resources with experience in turnkey design, supply, installation and commissioning of a power plant.
Additionally, the candidate must have “extensive experience” in generation plant construction and operation. The candidate will also have undertaken and successfully completed at least two similar projects over the last five years, with each of the two plants having been in successful operation for at least 10,000 hours by the time of tendering.
The candidate must also have been the main contractor in the turnkey design, supply, installation, and commissioning of at least five fossil fuel fired power stations or other “power islands”, with each such plant having been in successful commercial operation for at least 10,000 hours.
Unlike the power stations currently in use, the new plant will also be subject to stringent emission control levels in terms of the dangerous pollutants carbon dioxide, sulphur dioxide, nitrogen oxide and ammonia.
The new power plant’s design will also have to bear issues of noise and vibration emissions in mind. If the Delimara location is selected, the candidate will have to consider such emissions in light of the fact that another power station will be functioning on the same site and that inhabited buildings, such as the summer residence of former prime minister Dom Mintoff, are located on the perimeter of the power plant. If another site is chosen, it will have to consider the effect of noise and vibrations on residential, commercial and industrial activities in the vicinity.
Network stability requirements are also being enforced, with a tender condition stipulating that the plant has to be designed so that any single fault leading to an unplanned power outage will not result in more than a 50 per cent loss of the total block electrical output.
Enemalta also stipulated that the completion of works should not exceed 24 months from the signing of the contract to its full commercial operation. The plant’s operations will be subject to performance and efficiency guarantees backed by imposition of penalties.
The end result of the tender process will be one single contract for the whole project to be signed between one successful candidate and Enemalta.