The work on Manwel Dimech Bridge involves the demolition of the super structure, rehabilitation of piers and abutments, reconstruction of superstructure and re-alignment of adjoining roads.

How will the work be carried out?

The work mentioned above will be carried out in two main phases, which will be further sub-divided into other phases, as required, during the works:

First Phase. Work will be carried out on the eastern viaduct (carriageway from St Julian’s to Valletta);

Second Phase. Work will be carried out on the western viaduct (carriageway from Valletta to St Julian’s).

How long is the work expected to last?

Work on the Manwel Dimech Bridge is expected to be completed by September 2007.

Will there be access across the bridge while the work is being carried out?

One viaduct is to remain open to traffic. However, unless it is really necessary, motorists are advised to follow the diversion and deviation routes being proposed. Traffic delays will be possible. Also, as per current practice, motorists are advised that the 45 km speed limit is being retained.

How can I plan my route before hand?

In order to facilitate matters for motorists, the Authority has drawn up a whole list of alternatives that motorists should take in order to avoid the Bridge. Details of the alternatives are being featured on the Authority’s web-site and on the local media. The details will be updated accordingly from time to time.

While driving, how will I know which route to take?

The Manwel Dimech Bridge Diversion Routes will be very specific to the extent that temporary directional signage (yellow background) has been installed at critical junctions. This will enable motorists to take alternative routes well in advance. The signage will be complemented by a set of Variable Message Signs (VMS).

What are VMS?

These are electronic roadside signs which can change the message they display and show different messages depending on the prevailing circumstances.

What are VMS used for?

VMS are primarily used:

• to display dynamic information to drivers;

• to warn drivers of accidents and/or incidents on the road ahead;

• to provide warning of traffic congestion and unusual events;

• to warn drivers of roadwork zones;

• to warn drivers on speed limits;

• to provide information drivers may use to take an alternative route;

• as a parking guidance system;

• to ask drivers to limit travel speed;

• to warn of predicted duration of traffic queues;

• to provide information about road closures.

What are the benefits of VMS?

• they improve vehicles’ route selection;

• reduce travel time;

• mitigate the severity and duration of incidents;

• improves the performance of the road network;

• improves overall safety on the road.

Critical/peak times

The peak hour traffic flows according to the Tender Document are as follows:

Winter (October – June) weekdays – Morning 6.30 to 9am; afternoon 4 to 6pm.

Summer (July – September) weekdays – Morning 6 to 8.30am; afternoon 12 to 2pm. Friday, Saturday, Sunday and public holidays 7 to 10pm