Work on the Tigné tunnel is now complete and awaiting government certification.
The tunnel was built by Midi as one of the requirements in its contract with the government. Considerable delays in finishing the tunnel were the result of the major engineering work required to preserve the overlying Garden Battery, a 19th century fortification system, which was not originally scheduled for conservation according to the Outline Development Permit.
The tunnel is designed to cater for two-way traffic in an urban, built-up area and was built to the size and specifications stipulated by the Outline Development Permit and the scheme approved by the Malta Environment and Planning Authority and the Roads Department.