WasteServ Malta Ltd is a waste management company owned by the government of Malta, which was established in November 2002 to help Malta meet necessary standards of solid waste management and to provide adequate infrastructure. In just five years, WasteServ has managed to complete the implementation of most of the urgent tasks mentioned in the Solid Waste Strategy for the Maltese Islands, which was published in 2001 and sets the agenda for sustainable development for the islands.
First of all, it has to be said that municipal solid waste (household) collected in Malta and Gozo is around 200,000 tonnes annually, while the population of the islands totals around 400,000 with a density of 1,282/km². This means that Malta is the seventh most densely-populated country in the world. Thus, the most difficult task for WasteServ has been to identify the locations of the required major waste management facilities and to have the sites permitted for development and for operations. The Nimby Syndrome proved to be a difficult task to overcome in large countries in Europe, and densely-populated Malta would fare no better. There is no locality where even the smallest waste management facility could be established, without finding resistance.
Dumps and engineered
landfills
One of the most pressing objectives of WasteServ since its inception was the closure of the two active landfills on the islands, situated at Maghtab and Qortin, before EU accession on 1 May 2004. This was essential in order to avoid having them registered as active landfills and subjected to stringent EU conditions, since it was physically impossible to make them compliant. When these landfills were closed, a number of related projects were initiated, namely:
• An alternative had to be found, and since 2004, WasteServ has developed and made use of the first engineered landfill on the islands. These were the Ta’ Zwejra Engineered Landfill, which was in use between April 2004 and December 2006, and the Ta’ Ghallis Engineered Landfill, which started operating in 2007 and is still in use.
• Rehabilitation of the old dump sites started being implemented, with the aim of converting these sites for recreation purposes. This included an air emissions project which had e8.3 million allocated and is being co-financed by EU Structural Funds through the European Regional Development Fund (ERDF). WasteServ’s commitment is to collect the hazardous gases and clean them before allowing them to be released into the atmosphere.
Waste treatment
WasteServ has also upgraded the Sant’ Antnin Waste Treatment Plant situated in the south of the island, again with the help of the European Union but this time through the Cohesion Fund. Once completed, the fully-enclosed upgraded plant shall include the following facilities:
• Waste acceptance station for the collection of data and control waste deposit at this site;
• Material Recovery Facility (MRF) for the manual sorting of dry recyclable waste recovered by the separation at source, which will accept a maximum of 36,000 tonnes annually;
• Mechanical Treatment Plant (MTP) to mechanically separate the MSW received, which will accept a total of 35,000 tonnes annually;
• Digestion and Stabilising (Composting) Plant, which would treat the source-separated biodegradable waste and mechanically sorted biodegradable waste from the MTP;
• Combined Heat and Power Plant (CHP), which will run on the biogas produced and return electrical power enough for 1,400 households of four persons each;
• Regenerative Thermal Oxidiser (RTO) to treat gases and odours generated within the closed compartments.
The recent introduction of the first Waste Thermal Treatment Facility at Marsa has eliminated the use of local mobile incinerators such as that at the Civil Abattoir, at St Luke’s Hospital and at the General Hospital in Gozo. Inaugurated in December 2007, the plant was co-financed by the Fifth Financial Italo-Maltese Protocol. The incinerator treats abattoir waste, hospital waste, refused derived fuel and industrial sludges. The plant operates in strict conformity to EU standards.
Waste separation
With regard to waste separation, WasteServ’s bring-in sites project has been a resounding success. The 200 bring-in sites in localities around Malta and Gozo, and another 200 bring-in sites in schools are being utilised by the public for the disposal of paper, plastic, glass and metal. With the help of the local councils, people are delivering clean, source-segregated recyclable materials, with an ever-increasing rate of response. Through these bring-in sites, in 2005, 2,555 tonnes of separated waste were collected and in 2006, there was an increase of 25 per cent (2,810 tonnes). Furthermore, a door-to-door collection for separated paper, plastic and metal is currently being introduced and this will surely increase once more the amount of waste being separated at source.
In addition, WasteServ has introduced (again with financial aid from the EU) new civic amenity sites that accept separated bulky waste from the public. These were also highly successful and have led to a reduction in the amount of waste going to the landfill. Such sites are centres where households can conveniently dispose of their separated waste such as furniture, appliances and household hazardous waste among others. Three civic amenity sites have been in operation since early 2007 with two other civic amenity sites due to open soon. The amount of bulky separated waste collected through these facilities by the end of 2007 amounted to 8,396 tonnes, with more than 39,000 vehicles making use of the facilities.
WasteServ’s vision for the future is that of maintaining a strong commitment to provide a responsible and sustainable waste management service for the Maltese Islands. A detailed report on WasteServ’s five years of operation is available for download on WasteServ’s recently-revamped website: www.wasteservmalta.com.
Article provided by WasteServ