In past decades, it was always difficult for Maltese authorities to find the means of disposing waste generated on the island in a safe and sound way. To complicate matters, the public was brought up in a culture that as long as waste is no longer visible to the individual, the problem was “solved”. Landfills used to be established at all localities in an ad hoc manner, such as in Wied Fulija, Luqa, Marsascala, Mtahleb and Qrendi, until all waste started being directed to Maghtab.
It was soon realised, however, that such uncontrolled and non-engineered landfills could be creating serious health hazards, and that the conditions created by the mixed waste mass dumped at Maghtab and other closed landfills during the last 30 years could not be ignored. Thus, a decision was taken to start studying the negative impacts of these landfills.
What emerged is that these closed dumps, particularly those at Maghtab, Qortin and Wied Fulija, do consist of a mixture of municipal solid waste generated in Malta, but are mixed and covered with a large amount of inert waste. Also, due to the biological decomposition of the organic fraction in the waste, heat, methane and toxic gases were being released in the atmosphere.
The disposal of the various items resulting from the demolition of buildings provided cavities and passages for air to be flowing inside these dumps and internal fires became an ongoing thing, with temperatures reaching over 200oC internally. This process would also release excessive amount of carbon monoxide and dangerous gases resulting from the burning of our household and industrial waste.
The investigation of these sites revealed that intervention was needed in order to control and reduce the hazardous emissions and greenhouse gases from being released into the atmosphere. There were basically two possible main solutions. The first proposal was to seal the entire landfill to avoid oxygen entering into the dump, and the other was to allow natural internal degradation and then collect the gases generated by this burning and treat the gases before they are allowed to be released into the atmosphere for all of us to breath. Since it was practically impossible to ensure air tightness of such a large surface area at all seasons (circa 400,000 square metres!), WasteServ Malta Ltd. decided to go for the second solution. To reach this, however, developments costing millions of euros were needed and this was only going to be possible through European Union funding.
Controlling Aerial Emissions – The Project
The aerial emissions project, formally titled “Aerial Emissions Control for Maghtab, Qortin and Wied Fulija Landfills” introduced the latest technologies available to minimise any negative environmental impacts of these dumps. Co-financed through the European Union Regional Development Fund (ERDF), the budget allocated for this project was of about e8.8 million.
This project includes the construction of gas wells, pipe-works and gas treatment plants that would enable the successful collection and cleaning of hazardous gases before allowing them to be released into the atmosphere. The main benefits of the project are mainly the improvement of the air quality of the Maltese Islands, by treating dangerous gases such as dioxins and methane and also the reduction in odours. The results attained to date are very encouraging and may also be indicative of what we expect to achieve once the project is completed.
Latest Update
Currently, Maghtab is in the stage where most of the wells, which amount to around 350, have been installed and are being connected. Currently the dump is being studied so that further improvements could be made after the monitoring and assessment periods, most importantly to acquire information so as to decide on whether to install more wells in more effective areas. All major earth moving works have been completed, and while preparing adequate access to all gas wells and manifolds, general good structural stability has been achieved.
The drilled wells inside the dump are 12 metres deep, and they collect the gases from within the landfill by negative pressure. These wells are spread all over the landfill so as to make sure that most of the gases generated by fires within the landfill are being collected. All wells lead to a manifold, which in turn are connected to a main pipe that leads to the gas compound.
The RTO compound
The gas compound is where the major equipment stands and where these gases are collected, cleaned and then released into the atmosphere in a state which is not dangerous. This compound includes pumps, measuring instruments and a Regenerative Thermal Oxidiser (RTO).
Once the gases are collected, these are burned between ceramic plates at some 1100°C installed in the RTO, which alone cost around e1.4 million from the budget allocated to this project. The works for this system, that includes gas collection and treatment, is expected to be complete by the end of this year.
The ultimate objective
This process allows for the gradual conversion of the Maghtab site from a health hazard into a public recreational park, where visitors can enjoy open spaces and natural scenery. An international competition inviting proposed designs to determine the best possible development of the large Maghtab site was organised by the Ministry and the winning designs were those of German consortium Melitopia, who should be converting Maghtab into a recreational park.
This project is estimated to cost a further e30 million from EU funds and will be split into three phases. The landscaping along the cool and gas-free area in the vicinity to the edge bordering with the coast road has already started. Other areas are at an advanced stage of development to start having trees planted in the coming cool period.
Article provided by WasteServ
More information about WasteServ can be obtained by visiting website www.wasteservmalta.com or by calling the WasteServ Freephone 8007-2200