Following a 14-year battle against development plans for Gozo’s Hondoq ir-Rummien, the Moviment Harsien Hondoq (MHH) yesterday said it was “delighted” by this week’s unanimous Planning Authority’s Planning Board decision against the Qala Creek mega tourism project.
MHH spokesperson Paul Buttigieg said yesterday, “It has been a long 14-year struggle, and would not have been possible without the help and support of thousands of people. Everyone who wrote, spoke, signed petitions, and showed opposition to this project were all involved in helping. Everyone’s input made a difference. Thanks to each and every one of you.”
The MHH extended special thanks to the past and present Qala local Councils for their continued support, and to all the NGOs who assisted in the struggle against the development, including Flimkien ghal Ambjent Ahjar, Ramblers Association, Nature Trust, Din l-Art Helwa, FOE Malta and Zminijietna.
He warned, however, that “The window is still open for new applications to be submitted to develop Hondoq with ‘low density’ buildings due to the changes made in the 2006 Local Plan, which meant the area changed from an ODZ area ‘for agricultural use or afforestation’, to an area where ‘tourism and marine related development may be considered’.”

This change in the Local Plan, according to Mr Buttigieg, “was done without consultation with Qala Local Council, or the public, and according to Mepa’s Audit Office this lack of consultation should not have happened, considering the ‘substantial’ nature of the changes. “
MHH reiterated that it objects to any sort of development, “since once any sort of accommodation is built, a precedent will have been set for further construction to take place. Unless this loophole is closed, this saga will never end.”
Mr Buttigieg added, “In the light of the refusal, and the wishes of over 4,400 people who signed the petition, the area should now be returned to its original ODZ status. This would also fit in with FAA’s call to have Hondoq designated as being in the Public Domain, to be preserved in its natural state.”
The group also highlighted the issue of rubbish littering the area, a fact that the would-be developers had used to justify the area’s development – so much so, according to Mr Buttigieg, that photographs of old discarded fridges and tyres had been used during the application process.

“They (the failed developers) are responsible for cleaning the area, but they won’t as it suits their cause – even to the extent of refusing access to the Gozo Ministry which had tried to clear it up.
“An old tyre or fridge is not an excuse for a multi-million euro speculative development. The land should simply be tidied up,” Mr Buttigieg said.
He added “We would like to say a huge thank you to the Planning Authority for taking the logical and sensible decision to save Hondoq from being ruined by development - so we can all enjoy the beautiful coast that Gozo still has to offer. Please return the land to its original ODZ status now.”
The Planning Board’s refusal
On Thursday, the Planning Board unanimously voted against granting an outline development permit for the construction of a destination port comprising of a hotel, a yacht marina and a tourist village.
The Board cited that although the Gozo and Comino Local Plan promoted the rehabilitation of the damaged landscape, resulting from the past quarrying activity in Hondoq ir-Rummien, the type, scale and density of the proposed project by far exceeds the interventions considered acceptable for the area. Additionally, the Board also noted, that the project goes counter to the SPED’s vision for Gozo, that of being an ecological Island.

The proposed project with a total site area of over 103,000m2 was divided into several zones and consisted of a 110-bedroom hotel set on nine floors, 25 self-catering villas, 60 self-catering apartments, 200 multi-ownership accommodations consisting of apartments, maisonettes and bungalows, over 1,200 underground car parking spaces, a chapel, administration offices, shops and restaurants and a yacht marina for 150 berths. The project also included the refurbishment of the existing quay to make the swimming area more accessible to the public, improve the kiosk facilities, and create an underground public car-park, public toilets, shower facilities as well as upgrading the slipway facilities.
Following the conclusion of the EIA process with the recommendations of the then Environment Protection Directorate, the applicant had presented a revised master plan, which among a number of changes eliminated the marina but included the excavation to form a lagoon-type bathing area with a beach.
The Authority had informed the applicant that the new master plan constituted a material change and therefore could not be assessed as part of the planning application. Although the applicant had appealed the Authority’s decision not to proceed with a revised assessment, the Environment and Planning Review Tribunal had dismissed the appeal.